“The time has come,” the Dollhouse said, “to talk of many things…
Like, namely, when’re we gonna get the contractor paid for the roof?!”
Good question, Dollhouse, good question indeed. Who knew our house was a fan of Alice in Wonderland?
How Draws Work in a 203(k) Renovation–A Worst Case Scenario Guide
Now, if you’ll think back to when we first went down the 203(k) road (back in January), you might remember that there are several moving parts to the renovation side of the mortgage loan. It’s not just the contractor’s numbers and a bump for just-in-case, there are fees for the draw center, the inspections, and all sorts of other things. And it’s not like, once you close on the mortgage they hand you a checkbook for the renovation escrow account and say ‘Have fun, send us your receipts!’ (Would that it were that easy, seriously, this post probably wouldn’t exist if the bank actually trusted homeowners enough to do that.)
Instead, we have the contractor who has to do the work, the HUD Consultant to verify the work, and the Draw Specialist at the bank who metes out the funds like a la Scrooge McDuck (withholding 10% of each request until the bitter end just in case someone places a lien on our property in the mean time–I mean, I get it, but you have to admit it’s a fair comparison). Oh, right, and I sign all the forms for good measure, too.
The contractor’s office billed us for the roof (which was almost half of the total renovation contract) which triggered our HUD guy to schedule a time to go up and view the house. Of course, when he got up there, they weren’t quite finished and, since pictures have to be submitted to the bank with the draw request, the request was adjusted to 95% of the roof expense, to allow for the portion yet to be completed. He had the contractor initial the changes, sign the pages, and then brought the paperwork to my office before sending it up to the bank.
Had this been any other renovation project, that would have been all it took.
Since when has this process been anything other than difficult?
It seemed simple enough: the bank kicked the forms back because they were signed by Contractor L (our original guy) and not Contractor S (the one with the license that came on as supervisor). But the the HUD-C acts like he doesn’t know who this Contractor S even is, when–hello!–he had to redo the paperwork to put S’s name on the work order. Sure, that was a couple months ago, but check your notes, dude! It felt like being in my gastro’s office when he asks who’s monitoring my A1AC deficiency and I have to tell him he is! Grr!
So we forward the paperwork to Contractor S, only somewhere in the preceding 24 hours one of the forms has changed and now requires Contractor S’s signature be notarized. Now, I ask you, what contractor has time to go hunt down a notary in the middle of a project?! One that wants to get paid, obviously, but still, it meant an additional delay. Then the forms come back to me to sign and I send them up to our Draw Specialist to meet up with the photos that were already there. Of course, that wasn’t enough, the HUD forgot to date one of his signatures.
All of this started on Wednesday, and by Monday I still hadn’t received confirmation that the check had been cut. Meanwhile, Contractor L let me know that he’d done all he could until he got paid, which meant nothing was getting done on the house. Which, you know, I can’t really fault him because expenses were incurred, crews have to get paid, etc.; but I was a little peeved at the same time that the time we were ahead (thanks to the rapid turn on the roof) was being frittered away.
By Tuesday I was placing yet another request for update, which did get an eventual reply that if she had the updated signature then she could conceivably process the payment. Which was confusing since she’s replied Monday that they did receive the corrected paperwork on Friday! Turns out the Draw Specialist was out on Monday, one of her team members had replied in her stead, but since they didn’t copy her on the reply she didn’t know what was said. Even though it came from her own email address!
There was one more wrinkle about to come into play: I was leaving town Thursday night to head to Mobile for MobiCon. If the check didn’t arrive at my office early enough for me to drive it up to Thomasville (which is a 2 hour round trip) then it would be the following Tuesday before I could get it to him and he could get his crew back to work, if even then, what with the holiday and all. Thankfully the check did arrive on Thursday morning and I did spend 2 hours on the road just to get things moving again.
All in all it took over a week to fully process this first draw request and 1 week of lost work on the house. And while they say it’s random, I just got word that our project was selected for a Disbursement Quality Assurance Inspection on our HUD Consultant. What are the freaking odds?!
But, hey, at least we have a pretty new roof to keep the rain out and the floors are close to being fixed, now, too.
Back to our usual video updates next week!